A mold acceptance checklist is the list you work through before you release the final tooling payment. Once that balance is paid, you have nothing left to hold back: the shop has its money, and anything still wrong with the tool becomes a favor instead of an obligation. So the balance should follow evidence, not a message saying the samples look good. Here’s what we check on the samples, on the tool and in the paperwork before we tell a buyer it’s time to pay.
Generic illustration, not a part ProteForm made.
What does mold acceptance actually cover?
Accepting a mold means three separate things, and buyers often check only the first. The parts meet your drawing and cosmetic requirements. The tool runs steadily enough to make those parts shot after shot in production, not only on a good afternoon. And the tool you’re paying for is the tool that was quoted, with the paperwork you need to run or move it later.
Here’s the checklist we use, with the evidence that proves each point:
| What you are accepting | Evidence to ask for | If it is missing or fails |
|---|---|---|
| Parts meet the drawing | A dimensional report on the latest samples, per cavity, against your current drawing revision | No balance until the misses are fixed or you sign a deviation |
| Parts look right | Samples checked against your cosmetic criteria, with photos of each defect called out | Agree which defects are tool fixes and which are process fixes |
| The tool runs steadily | Video of the mold running in the press for a continuous stretch, plus the process sheet for that run | Ask for another trial before you treat the cycle as proven |
| You got the tool you paid for | Cavity count, steel and hot runner checked against the accepted quote; photos of the open mold and the nameplate | Raise it now. A cheaper steel or fewer cavities is a price change |
| You can run it elsewhere later | Mold drawings or design files as your agreement states, spare parts list, cooling and hot runner wiring layout | Hold that part of the balance until the files are handed over |
| Open points are written down | An issue list both sides sign: what is still open, who fixes it, by when | Without the list, open points tend to disappear once you pay |
Check the samples first
Everything starts with parts in your hands, measured against the current drawing. Ask for a dimensional report per cavity, and check a few critical dimensions yourself if you have the gauges. For appearance, judge against written criteria, not taste on the day. Cosmetic inspection criteria explains how to write them so both sides read a defect the same way.
Make sure the samples were molded in the production resin and color. A sample in a substitute grade can measure differently from what you’ll get in production.
Have your tool checked before you pay the balance
Send the drawing, the accepted tooling quote and the latest sample report or photos. We’ll tell you what’s missing from the evidence and what to ask the shop for. For new tooling, we confirm the producing factory and write the acceptance terms into the order before we quote.
Check the tool itself
You don’t need to be a toolmaker to do this. You need the accepted quote open next to you, and either a visit or a video call with the mold on the bench or in the press:
- Cavity count and cavity IDs. The number of cavities matches the quote, and each cavity marks its number on the part so you can trace a bad part to its cavity. See mold markings and date codes.
- Steel. If the quote named a steel grade for cavities and cores, ask how the shop confirmed it: the steel supplier’s material certificate, a hardness check, or both. Our mold steel guide explains why the grade matters for tool life.
- Hot runner, if quoted. Brand, number of drops and the controller. A later shop needs this to run the tool. Background in hot runner vs cold runner.
- Nameplate. A plate on the mold with the tool number, part number, cavity count and, if agreed, your company as owner.
- Cooling circuits. In and out ports stamped or tagged, so the water lines go back on the same way after maintenance or a move.
- Surface condition. Texture or polish on the cavity matches what was agreed, and no visible repairs on show surfaces that nobody told you about.
- Ejection and moving parts. Slides and lifters move cleanly, and parts drop or are picked without being forced off. Marks left by pins are covered in ejector pin marks.
Documents to hold before the balance goes out
These are the papers that let you run the tool at another shop someday, or settle an argument about what was approved:
- The final dimensional report and your signed sample approval, both tied to the drawing revision they were checked against.
- Approved reference samples from each cavity, labelled and kept by both sides.
- The process sheet from the approved trial: resin grade, drying, temperatures, pressures and cycle as actually run.
- Mold drawings or design files, to the extent your ownership agreement says you get them. Who owns the mold covers how to write that.
- A spare parts list, with which spares were included in the price and which you would buy later.
- A record of every steel change made since T1, with the reason for each.
How the acceptance sequence usually runs
Agree the acceptance terms before the tool is built
The best time to write the checklist is when you accept the tool quote. Name the sample stage that triggers the balance, the evidence you need and who signs off. Tooling payment terms covers how to tie each payment to an event.
Review the T1 samples and report
Measure, compare against the drawing, and list every miss. Our guide to reading a T1 dimensional report shows what to look for. Many tools need a round of steel adjustment after T1, so don’t treat T1 as the acceptance point unless the samples really are clean.
Fix, retrial, re-measure
After corrections, ask for a new report on the new samples, not a marked-up copy of the old one. Check that the fixes didn’t move something else.
Walk the tool and the paperwork
Go through the tool checks and documents above, in person or by video. Photograph the nameplate, the open mold and the cavity numbers.
Sign the acceptance record and the issue list
One page that says what was accepted, against which drawing revision, and what is still open. Then release the balance.
Mistakes we see at mold acceptance
- Paying the balance on photos of parts only. A photo says nothing about dimensions or how the tool runs.
- Accepting samples molded in a different resin grade or color than production will use. Shrink and appearance can change.
- Letting the report cover one cavity of a multi-cavity tool. Each cavity is its own piece of steel.
- Approving samples against an old drawing revision after a change was agreed by email.
- Combining the tooling balance and a first production deposit in one payment, so neither can be held back on its own.
- Keeping no reference samples. Six months later nobody can say what the approved part looked like.
If the tool is staying in the shop for production, ask how it will be maintained and who pays for wear parts before you sign off. Mold life and maintenance lists the questions. If a design change is coming soon after acceptance, settle how it will be quoted first; see design changes after the mold is made.
Frequently asked questions
When should I pay the final tooling balance?
After the samples you named in the order are approved in writing and the evidence on your checklist is in hand. That is often after T1 corrections, not at T1 itself. There’s no standard stage; pick one, write it into the order and stick to it.
What is a mold acceptance report?
A short signed record that says which tool was accepted, against which drawing revision, based on which samples and reports, and what is still open. It is the document you point to later if the tool is moved, modified or disputed.
Can I accept a mold that still has small issues?
Yes, if they are written down. Sign an issue list that names each open point, who fixes it, who pays and by when. You can also agree to hold back part of the balance until those points are closed.
I can’t attend the mold trial. How do I accept the tool?
Ask for video of the mold running continuously in the press, photos of the open mold and the nameplate, the process sheet, and the dimensional report with samples shipped to you or to an inspector you trust. Approve against the samples you hold, not the photos alone. Our remote mold trial guide lists the photos, video and data to ask for at each trial round.
Does accepting the mold mean I own it?
Not by itself. Acceptance confirms the tool works. Ownership, storage and release rights come from what the order or a separate agreement says. Read who owns the mold before you pay.