What to Do When T1 Samples Fail Dimensional or Cosmetic Checks

Resources / Buyer’s Playbook / What to Do When T1 Samples Fail

The first shots from a new mold came back, and some of them failed. A dimension is out, or a face that should be clean has sink, flash or blush. The temptation is to recut the steel at once, or to sign off because you need parts next month. Either call can be right, and either can lock you into the wrong cost. This page is the decision path after T1 samples fail. If you still need to read the report itself, start with our guide on how to read a T1 dimensional report.

Engineer checking a drawing against a part with a height gauge and calipers on a granite inspection bench

A typical inspection bench: drawing, height gauge and calipers.

Sort the failures before you pick a fix

A failed T1 is a list of features, and they often point in different directions. Sort them before anyone touches steel or you waive a line. We start with five questions:

  • Is it dimensional, cosmetic, or both? A hole that won’t take a screw is a different argument from swirl on a hidden rib.
  • Is it one cavity or every cavity? A miss in one pocket usually lives in that pocket’s steel. The same miss in every pocket is more often process, resin or a plate-level issue.
  • Is it one feature or a pattern? One balloon out, in a steel-safe direction, is often planned stock. Related dimensions all leaning the same way may be shrink, pack or warp, not a single milling error.
  • Does it move when the molder changes settings? If a short pack or a hotter melt brings the feature into band and the rest of the part still looks right, start with process. If it only comes in when something else starts to fail, the steel or the design is in play.
  • Did you actually specify the cosmetic limit? A “fail” on a face with no surface class, viewing distance or limit sample is a criteria gap, not automatically a tool defect.

If you weren’t at the trial, get the photos, uncut video and process sheet first. Our note on what to ask for at a remote T1 mold trial lists the evidence that helps. Don’t approve, or reject, from a tidy photo set alone.

Which path: tool fix, process change, deviation or drawing change?

Our T1 report guide names four usual routes once a line is NG. The work is choosing the right one. Use this table as the decision, not as a stand-in for looking at the parts.

What you’re seeingPath to takeDon’t do this first
One cavity, one feature, material in a steel-safe direction (hole small, boss tall, wall thick)Tool steel adjustment, then a T2 measurement of that feature and its neighborsWaive it “for now” on a fit or sealing face. Planned stock is meant to be cut, not ignored.
Every cavity, same feature, and the reading moves when pack, melt temperature or hold time changesProcess window first. Record the settings that work, and check that cosmetics and other dimensions still passCut steel because the first shot was out. You may be machining away a process issue.
Feature is out, it doesn’t affect fit or function, and you can live with the valueA written deviation for that balloon, that value and that reason. Keep it attached to the sample approvalA verbal “it’s close enough.” That disappears when a later lot is disputed.
The tolerance is tighter than the part needs, or the drawing fights how the plastic actually shrinksRevise the drawing. Measure the next samples against the new revisionAsk the toolmaker to “just make it to print” when the print is the problem. See drawing tolerances before you tighten a band again.
The miss is past a steel-safe tweak: a shape change, a new rib, a moved hole, a weld or insert in the toolTreat it as a design change after the mold is cut. Agree scope and cost before the steel is weldedCall a redesign “T1 correction” so the toolmaker absorbs a product change.
Cosmetic only: flash, witness, pin marks, blush, or texture that doesn’t match what you thought you’d getJudge it against written cosmetic inspection criteria and, if you have them, limit samples. Then decide: tool polish or texture, process, or a criteria updateReject the whole tool on a face you never classified, or accept a defect on a sealing or wear edge because “it’s only cosmetic.”

Work the list in this order

This is the sequence we use. Cheapest to check first, hardest to unwind last.

1

Put the evidence in one pack.

You want the ballooned drawing at the released revision, the report (a spreadsheet is easier than a scan), photos of each failed feature with the cavity number visible, the process sheet, and how long after molding the parts were measured. If the resin is moisture-sensitive, that last point matters. Keep a few parts from each cavity.

2

Confirm the report is about the parts in front of you.

Match revision, cavities, units and datums before you argue a number. Quite a few “failures” are a header problem: the wrong revision, mixed units, or a feature measured in the wrong setup. That’s why the report guide starts with the header.

3

Split the list into four piles.

Tool, process, written deviation, drawing change. A single T1 can have all four. Don’t let a deviation on a non-critical rib quietly cover a sealing land that’s also out. If a feature needs a CMM to be trusted, say so; our CMM inspection note covers when that is worth doing.

4

Agree the path in writing before steel is cut or a waiver is implied.

A short punch list is enough: balloon, current value, agreed action, who does the work, what T2 must show, and who pays. If the tooling balance is still unpaid, tie open dimensional items to that payment. The mold acceptance checklist is for that moment.

5

Re-measure what you changed, and the neighbors.

A steel cut that opens a hole can thin a wall or shift a related feature. A process change that saves one dimension can create sink, flash or warp somewhere else. T2 is not “re-run the one NG line.” Re-check those lines, plus anything that could have moved.

Send your T1 report and drawings for a second look

Attach the report, the ballooned drawing and photos of the failed features. We’ll help you sort tool work from process work from a drawing change, and say so if this isn’t a job for us.

Who usually pays?

There is no universal rule, and we won’t invent one. What you agreed in the tooling quote and the mold-acceptance terms is what matters. These patterns are common:

  • On a new tool, bringing a steel-safe feature to the drawing you already approved is normally the toolmaker’s work, done before you accept the tool and pay the balance.
  • Process settings that were never stabilized, or a first shot run “hot and hard” just to fill, are the molder’s to sort out. Get the window written down.
  • A product change (moved hole, added rib, new finish, a tighter band you didn’t have at kickoff) is a design change, and the cost conversation is different. That’s the design-change page, not a free T1 correction.
  • A cosmetic reject against a standard you never wrote is partly on you. Write the criteria, then hold the shop to them.
  • Wear or drift on a tool that already ran accepted parts is a maintenance issue, not a T1 issue.

If the thread is already “you pay / they pay” with no punch list, stop and write the list first. The money argument is shorter once each line has a cause.

Cosmetic fails need their own argument

Dimensional NG is relatively clean: a number, a band, a method. Cosmetic NG is where T1 reviews stall, because two people can look at the same face and disagree. Before you send the tool back for polish or a texture recut, check three things.

First, did the drawing or the RFQ name the surface class, viewing distance and light? If it didn’t, you’re negotiating a standard after the fact. Second, is the defect on a functional edge (a snap, a gasket land, a wear face) or on a hidden wall? Flash or a pin mark in the wrong place is not “only cosmetic.” Third, do you have a limit sample, even a temporary one? Write the criteria down; our cosmetic inspection criteria page is the place. Don’t fail a tool for a texture that hasn’t been cut yet, and don’t approve a textured face off a single flattering photo.

What to send the molder (or us) after a failed T1

Include:

  • The released 2D, ballooned, with the failed balloons marked.
  • The T1 report, preferably as a spreadsheet, plus photos of the measuring setup for unusual callouts.
  • Photos of each failed feature, both cavities if they differ, with a scale in the frame when size is the issue.
  • The process sheet and, if you have it, video of filling and ejection rather than a staged group photo.
  • Your proposed split: which lines you think are tool, process, deviation or drawing, and why. Unsure is fine. Skipping the split is not.
  • Any mating part, gauge or functional test you already ran, and the result.

If the drawings are export-controlled, don’t attach them to the public form. Send a short non-confidential summary first and see our controlled project requirements.

When this isn’t a job for us: if you need a same-week recut on a tool at a shop we didn’t place, that shop will be faster. If the only question is a commercial waiver on a lot already at the dock, that’s between you and the current supplier. And if you want us to “just get the parts shipped” with open fit issues and no written deviation, we won’t.

Frequently asked questions

Can I approve T1 with a deviation and fix the tool later?

Yes, on features that don’t affect fit, function or safety, if the deviation is written: balloon, value, reason, and whether production may ship to the same value. Don’t use a temporary waiver as a quiet way to skip a steel-safe cut on a feature you still need in spec.

How many T2 or T3 rounds should I expect?

There’s no honest fixed number. One clean steel-safe correction can be enough. A mix of process, cosmetics and a drawing change can take more than one loop. What you can demand is a punch list, a re-measure of the changed features and their neighbors, and a stop if the same line fails for a new reason each time without a cause.

Should I accept a verbal “it’s close enough”?

No. If you’re going to live with a value, write it down. A verbal pass is hard to enforce on the next lot, and it’s useless if you later transfer the tool. The same goes the other way: if you reject a feature, say so in the same note, with the balloon and the reading.

Do I have to re-run the full dimensional report after a steel change?

Re-measure every feature you changed, plus anything that could have moved (neighboring walls, related fits, warp-sensitive spans). A full re-balloon of every non-critical line is not always required, but “only the one NG balloon” is usually too thin. Agree the T2 scope on the punch list.

Send T1 samples and drawings for a project review

If first-off-tool parts failed and you want a second look, send the report, the drawing and the photos. We’ll say what should be tool work, process work or a drawing change, and whether ProteForm is the right coordinator for the next step.