If you buy molded parts from China, Chinese New Year production delays are not something you should discover in January. Many shops shut or slow around the holiday, and the effect starts before the first official day off and can continue after people return. Lunar New Year 2027 begins on 6 February 2027. That is the festival date, not your supplier’s shutdown calendar. Ask that shop for its actual holiday dates, then plan steel, resin, approvals, and freight around them.
Generic illustration, not a part ProteForm made.
How does Chinese New Year affect plastic parts lead times?
Chinese New Year is a holiday with a calendar date, and it is also a production event that is wider than that date. Before the festival, shops finish running lots, close tools, and send workers home. After the festival, people return in waves, presses are brought back up, and a queue of work is waiting. Your part is in that queue with everyone else’s.
The festival date is knowable in advance. Lunar New Year 2027 begins on 6 February 2027. What is not knowable from a public calendar is how long any one shop will be down, who will be back on which day, or whether a particular toolmaker, a steel supplier, or a freight lane will move at the same pace. Official public holidays and a given shop’s own close-down are not the same thing. Some shops post a notice. Some only tell you when you ask. Ask, in writing, and keep the answer with the project file.
This is one input to a mold and production schedule, not the only one. Part complexity, steel, approvals, and shipping still matter. We cover those on the injection mold lead time page. The holiday does not replace that picture. It sits on top of it, and it will punish a plan that assumed the shop would be working as usual through early February.
Why you should not assume a standard shutdown length
Buyers often hear a single number for how long China is closed and build a plan around it. That is a poor method. Shops do not all close on the same day, they do not all reopen on the same day, and a tool shop, a molder, a resin house, and a finisher in the same project may not share a calendar.
Do not treat a length you heard on another program as this supplier’s plan. Do not treat the first day of the lunar year as the first day the shop is closed, or the first working day after the official holiday as the day your parts will ship. Some work winds down earlier because steel or resin will not arrive in time. Some work restarts later because a key person, a sub-supplier, or a customs queue is not yet back to a normal pace.
The practical move is to request that shop’s holiday calendar for this year, including the last day they will accept a new purchase order or a design freeze for work they still intend to finish before the break, and the first day they expect to be running your kind of work again. If they cannot give you that, you do not have a schedule. If you already have more than one shop on the same program, ask each of them. A date that works for the toolmaker may not work for the molder, the painter, or the assembler downstream.
Send drawings so we can plan around the holiday
Say so if Chinese New Year sits inside your need-by window, and give us the date the parts actually have to be in your hands. Send the model or drawing, material, quantity, and whether a tool already exists. We’ll review the design, confirm a supplier, and only then quote, including an honest view of whether the holiday is in the way. We will not invent a shutdown length to make a date look safe.
What should you freeze before the break, and what should you pull in?
The work that gets hurt most is work that is half finished when the shop winds down, or work that still needs a bought item that will not arrive in time.
| When | What to settle | What goes wrong if you skip it |
|---|---|---|
| Well before the festival date | Ask that shop, in writing, for its holiday calendar, the last day it will accept a PO or a design freeze for pre-break work, and when it expects to run your kind of work again | You build a plan around a date that does not match this supplier |
| While steel, resin, or inserts are still on order | Confirm those items will arrive in time for the shop to use them before it winds down, or accept that the job waits until after the return | A tool or a lot sits because a bought item missed the last useful receiving date |
| While a design or a recut is still open | Freeze a revision the shop can finish and close, or agree in writing that the change starts after they return | A mold is left mid-change or mid-weld over the break, and the restart is messy |
| When first shots are about to leave the shop | Close the approval with time to spare, or agree that the next cut is an after-holiday task | Your comments arrive when the toolmaker is already gone, and the correction waits |
| After people start to return | Plan for inspection, packing, and freight to be busy, and know who books the shipment under your Incoterms | Parts are molded, then sit, or a sailing is missed, because the post-holiday queue was not in the plan |
The table is the plan. Do not pull in a PO if the shop cannot actually use it in time, and do not leave a mold mid-change or mid-weld over the break. If a design change is still open, freeze a revision the shop can finish and close, or agree in writing that the change starts after they return.
What happens after the holiday: inspection, freight, and quiet inboxes?
The first days back are not a normal week with a different date on it. Work restarts, but not all at once. Inspection slots, packing, and freight bookings can queue up, because many buyers wanted their lots to move at the same time. How that shows up on your desk depends in part on the Incoterms you agreed: who books the freight, and where risk passes. If you have not settled the term, do it before you are arguing about a missed sailing. Our page on packaging and shipping molded parts covers the packing and handoff mechanics.
A quiet inbox around the holiday is common, and it is not always a warning sign. Ask for the calendar before the quiet starts. If a supplier goes silent beyond the dates they gave you, or never gave you dates and then disappears, treat that as a supplier-not-responding problem, not as an extended festival. The holiday explains a planned pause. It does not explain a shop that cannot be reached when they said they would be back.
How we plan a project around Chinese New Year
We work with a network of factories in China, so there’s no single plant calendar. When we confirm a supplier for your part, we ask that shop for its holiday plan for the period that affects your job, and we put what they told us into the schedule we quote. We will not substitute a generic figure for how long China is closed, because we do not have one that is true for every shop.
If your need-by date and the holiday are in conflict, we will say so. Sometimes the honest options are to start earlier, to ship a partial lot, to fly a smaller quantity, or to accept that the parts arrive after your event. Sometimes there is no honest way to hit the date, and we would rather decline that promise than dress it up. We still need a model or drawing, material, quantity, and the date you actually need the parts, with a note if that date is a hard event. If you already have a shop calendar, send it. If the tool already exists, say where it is and whether a change is still open.
When we are not the right fit
If you only wanted a single printed calendar of when China is closed in 2027, we do not have one, and we will not invent shutdown dates to fill a slide. If you need a freight forwarder and nothing else, that is not our job. If the shop is already closed and you need parts during the shutdown, we cannot create capacity that is not there. And if you want a need-by date we cannot honestly meet, we will say no to that date rather than take the order and hope.
What to include in an RFQ when the holiday is in play
- The model or drawing, material, and quantity.
- The date you need parts in your hands, and whether that date is a hard event.
- Whether this is a new tool, a recut, or a repeat lot on an existing mold.
- Whether the current revision is frozen, or a change is still open.
- Preferred Incoterms, if you have them.
- Any holiday dates your current shop has already given you.
Frequently asked questions
When is Chinese New Year 2027, and does that tell me when the factory shuts?
Lunar New Year 2027 begins on 6 February 2027. That is the festival date. It is not a given shop’s shutdown start or end. Ask that supplier for its actual holiday calendar, including the last day it will take work it still intends to finish before the break.
How do Chinese New Year production delays affect a new mold versus a repeat order?
Both can be delayed, but they fail in different places. A new mold is hurt by steel and design-freeze timing, and by a tryout that lands in the shutdown. A repeat order is hurt by resin, press time, inspection, and freight. In both cases, a PO and a frozen revision have to arrive early enough for the shop to use them.
Should I place my PO before the holiday even if I do not need the parts until later?
If the shop must buy material or reserve time before it closes, yes, you should talk about that now. A PO by itself does not help if the drawing is still changing or if the shop cannot start the work in time. Ask what they need, and by when, rather than sending paper on the last afternoon.
Why is my supplier slow to reply around Chinese New Year?
Many shops are closing, already closed, or just back and clearing a backlog. If you were given dates and the silence fits those dates, wait and follow up when they said they would return. If you were given no dates, or the silence runs past what they told you, handle it as a supplier who is not responding.
What should I send so you can plan around the holiday?
The usual RFQ pack, plus the date the parts must be in your hands and a note if a tool already exists or a change is still open. If a current shop has already sent you its holiday dates, include them.
Send drawings so we can plan around the holiday
Say so if Chinese New Year sits inside your need-by window, and give us the date the parts actually have to be in your hands. Send the model or drawing, material, quantity, and whether a tool already exists. We’ll review the design, confirm a supplier, and only then quote, including an honest view of whether the holiday is in the way. We will not invent a shutdown length to make a date look safe.